CASE STUDIES
Non-Profit
IT Radio Satellite System Project Case Study
Project Description
Radio Satellite System Project's
Challenges:
- Assign tasks related
to multiple, concurrent projects in support of the program
to self and others across organizations within Distribution
- Evaluate project status,
analyze resource requirements, and determine need for
outside resources
- Manage project tasks
requiring awareness of multiple technical and business
disciplines
- Manage and escalate project issues to Distribution
management
- Negotiate and oversee consultant, contractor,
and vendor contracts in consultation with other management
and PRS’s Legal staff
- Prepare project budgets
- Coordinate staff assignments with PRS
department heads
- Prepare and present project status and
budget reports to the Distribution Deputy Director of
Projects and other Distribution management. Serves as
principal project liaison with Distribution executives
and managers
- Prepare and present informational sessions
to program producers and stations
- Coordinate execution of program communication
plan with Division members and external customer committees
- Manage multiple project teams in support
of the program by developing clear objectives aligned
with the program goals
- Institute technical delivery procedures
and methodologies across software and broadcast engineering
disciplines.
Challenges:
Solution(s) Provided:
- Get the project back on schedule
- Provide a detailed implementation project
plan – all the activities PRS needs to complete
to successfully deliver the PRS project, including critical
path and external dependencies.
- Provide an action item list – manage
the list of issues or action items to keep the plan on
target. Include PRS risk issue to be worked and responsibilities
assigned.
- Provide weekly status reporting –
communicate internally and externally the status of the
program progress
- Provide standard operating procedures
– standard operating procedures for Distribution
Information Systems staff.
Benefit:
- Managed the infrastructure of the PRS hardware
and software delivery systems to help support future producer
and station operations.
- Managed and controlled the upgrade of
the infrastructure and support systems for the Radio Satellite
System.
- Developed a workable project plan to get
the integrator back on schedule
- Negotiated and oversaw
consultants, contractor, and vendor contracts in consultation
with other management