Critical
Chain
CRITICAL CHAIN METHOD
- Improve systems
- Recognize dependency variation and finite
capacity that exists in the systems
- Understand that seemingly complex cause
and effect occurs via these dependencies, both in time
and in space, (i.e., dynamic complexity)
- Increase productivity and output at a
constant investment of money, manpower, and machinery.
Knowing that variable costs (raw materials) will increase
in proportion to output, but operating costs should
stay the same
Back to top
- Take all forms of padding out of activity
estimates and move to dedicated time estimates.
- Level project resources – don’t
schedule the project assuming that resource conflicts
will resolve themselves. We take care of this up
front.
- Avoid measuring people on the completion
of their activities on time or on the accuracy of their
estimates. Instead, we help you reward team members based
on finishing the overall project on time or early.
- Let people work on Critical Chain activities
in a dedicated manner. If someone is schedule to work
on one of these activities, let him/her work on it exclusively
until it is complete or substantially complete to the
point where it can be turned over to the next scheduled
resource.
- Change your resource management approach
so that resources on the Critical Chain have more flexibility
to accept work earlier than expected.
- Implement a project buffer to project
the project’s Critical Chain. This is usually put
at the end of the project and is calculated as a percentage
of the length of the Critical Chain – usually 30
to 50 percent. It’s a buffer that protects the collection
of Schedule Activities on the Critical Chain from any
common cause variations.
- Implement feeding buffers on any path
feeding into the Critical Chain to protect it from variances
on the feeding paths.
- Identify the Critical
Chain
– the longest chain of dependent Schedule Activities
where the dependency is either activity or resource
related. There are two possible paths for each activity:
first, what is the next logically dependent activity? –
You can’t pour footers until they have first been
framed up. And secondly, what is the next activity that
uses the same resource as the one where the dependency
is therefore a resource dependency? – The procurement
person for any project can only order one thing at
a time.
- Examine
– the duration of each possible path and select
the longest path based on resource or activity dependency.
- Create Buffers
– which act as shock absorbers. Reducing overall
project risk.
Back to top
We conduct Buffer Management using
the Critical Chain Method
- Any Schedule Activity on the Critical Chain
completed early increases the project buffer time by the
same amount. Any Schedule Activity on a feeding
path that finishes early increases that amount of time
to the feeding buffer assuming of course that the down-stream
resource is flexible enough to take advantage of an early
finish from a previous activity.
- Buffer management should be rigid. The
first priority is the current Schedule Activity that is
penetrating the project buffer, and the next priority
is the activity that is currently penetrating a feeding
buffer.
- In cases where there are critical milestones,
where bonuses or penalties depend on meeting them, there
is another priority called the “milestone”
buffer. It behaves much like the project buffer. This
buffer protects a subset of the project and is almost
like a mini-project within the bigger project.
Back to top
Managing the Execution of a Critical
Chain Project
- When the Schedule Activity is started
- How many days are left to complete the
activity
- When the activity is completed
Back to top |
|